Adolescent Behavioral Health Unit

Begin Construction: September 2024
Anticipated Opening: Mid-2025

Click here to learn more.

Rendering of nurses station.

Rendering of nurses station.

Rendering of BH shared patient room.

Roof Replacement

Begin Construction: May 2025
Anticipated Opening: August 2025

MRI Replacement

Begin Construction: September 2022
Anticipated Opening: November 2025

MRI Replacement

Central Plant Medical Vacuum System Rep

Begin Construction: July 2025
Anticipated Opening: December 2025

Central plant medical vacuum system replacement

Elevator Modernization

Begin Construction: May 2025
Anticipated Opening: February 2026

Elevator modernization

Central Plant-Cooling Tower Replacement

Begin Construction: September 2025
Anticipated Opening: October 2026

Central Plant cooling tower replacement

Hybrid Bi-Plane Angiography Suite and Operating Room

Begin Construction: June 2025
Anticipated Opening: Mid-2027

Areas of Focus: Outpatient Second Floor

Click here to learn more.

Rendering of bi-plane machine.

Other Active Construction Projects

Dates are subject to change.

CT Scanner Acquisition

Begin Construction: March 2025
Anticipated Opening: September 2025

Fire Door Magnetic Hold Open

Begin Construction: August 2020
Anticipated Opening: July 2025

Air Conditioning Sterile Department

Begin Construction: December 2025
Anticipated Opening: March 2026

Data Room Cooling System Replacement

Begin Construction: July 2025
Anticipated Opening: January 2026

Sonic Irrigation Replacements

Begin Construction: October 2025
Anticipated Opening: April 2026

Telemetry Expansion

Begin Construction: January 2026
Anticipated Opening: August 2026

Transfer Switch Replacement

Begin Construction: September 2023
Anticipated Opening: June 2025

Ligature Risk CMS Requirement

Begin Construction: September 2020
Anticipated Opening: October 2024

Linac Replacement

Begin Construction: November 2025
Anticipated Opening: April 2026

Replacement Deaerator#1

Begin Construction: August 2025
Anticipated Opening: December 2025

PA System Upgrade

Begin Construction: November 2025
Anticipated Opening: February 2027

Nurse Call System

Begin Construction: December 2025
Anticipated Opening: February 2028

Sterilization System Installation

Begin Construction: October 2025
Anticipated Opening: April 2026